INDUSTRIAL PROJECTS Dawson Coal Mine Infrastructure
Rollover thumbnails to view
Project Information:
Project                Dawson Coal Mine Infrastructure
Duration              2006
Man-hours         21,000
Manning Peak   20
Contract Value $3,700,000

Description
Stowe Australia provided the installation of HV, LV, E & I services to Dawson North, Central and South Mine locations.
The project was a design and construct fast track project and demonstrated the company’s overall depth of commitment and available resources in agreeing and achieving the challenging project construction program.