DEFENCE PROJECT
Fuel Farm Upgrade RAAF base Williamtown
Project | Fuel Farm Upgrade RAAF base Williamtown |
Duration | 2005 – 2006 |
Man-hours | 13,000 |
Manning Peak | 8 |
Contract Value | $1,400,000 |
Description
The works include FF3 and FF3A upgrade controls, electrical and instrumentation, Fuel Hydrant system AEW & C Apron, Design and audits, Substation upgrade, Civic works – excavations & under-bores, Underground conduits and pits, Consumer mains (within substation) & existing sub-mains re-terminate, LV Switch Board, New sub-mains, New MCC2, DB P1 at FF3 & new MCCB at FF3A, Earthing system for FF3, Lighting up-grade FF3 and FF3A, Cable ladders and supports, Power supplies, ESD controls & Instrument cabling, Fibre optical cables for PLC communications, PLC and SCADA – supply, install and programming, ENRAF and SAAB modifications, Alarm systems FF3 and FF3A, Testing and commissioning of above services