COMMERCIAL PROJECT
Margaret Court Arena, Melbourne Park
Project | Margaret Court Arena, Melbourne Park |
Duration | February 2013 – November 2015 |
Man-hours | 74,000 |
Manning Peak | 55 |
Contract Value | $17,000,000 |
Description
Stowe Australia and Lend Lease delivered the first stage of the upgrade to the Melbourne Park precinct.
This involved the transformation of Margaret Court arena from an outdoor court to a State of the Art fully enclosed stadium complete with Opening roof, Feature lighting throughout, food and beverage outlets , meeting rooms and new Davis cup function area.
Stowe Australia s scope included the complete installation of the Margaret court sports lighting to meet international standards suitable for tv coverage and the Australian Open Tennis.