ROLL OUT PROJECT
Fujitsu Coles Express Communications
Project | Fujitsu Coles Express Communications |
Duration | 6 months |
Man-hours | 11,200 |
Manning Peak | 14 trades persons across 5 states and 2 territories |
Contract Value | $700,000 |
Description
The works associated with this project consisted of the supply and installation of a new Point Of Sales system through out Coles Express sites across Australia. Stowe personal were not only involved with the site installation phase of works but also design and design implementation.
Stowe took a National approach to these works appointing a national project manager who was stationed at Fujitsu Sandringham offices who liaised with designated state project managers to ensure that the project was completed on time and to the client’s expectations.