South East Queensland Preparatory School
Project | South East Queensland Preparatory School |
Duration | 2005 to 2007 |
Man-hours | 60,000 |
Manning Peak | 25 |
Contract Value | $7,600,000 |
Description
The South East Queensland Prep School Rollout consisted of the installation of new, and refurbishment of existing building Each of the 300 + schools required an initial investigation and audit to determine actual the requirements.
Once the design was completed and approved the works were then carried out taking approximately 8 to 10 weeks to complete. All the new buildings require new electrical sub-main cables, fibre optic backbone cable for the computer network, copper backbone cable for the telephones and a security network cabling for the security system.
The scope of the refurbishments varied subject to the existing installation, but the end result was to provide all of the facilities that a New Building provided.