The Canberra Hospital, TCH Building 15
Project | The Canberra Hospital |
Duration | April 2015 to November 2015 |
Man-hours | 9,350 |
Manning Peak | 15 |
Contract Value | $1,400,000 |
Description
Works Executed under the contract comprised of the supply, installation, testing and commissioning of the complete electrical and communications services installation including:
Design and install temporary site electrical infrastructure to provide a safe and pro-active, energy efficient site through the use of 24v temps.
Installation of new certified Body Protect Power Distribution.
Installation of new General Power.
Installation of new Essential Power.
Installation of new Lighting and Lighting Control Clipsal Dali.
Installation of Monitored Emergency Lighting.
Installation of MSSB sub-mains and cable pathway.
Installation of new Distribution Boards.
Installation of new CAT 6A Structured Cabling.